legal background:
Article 2(8) of KM Decree No 20/1984 (III.21.) on the regulation of traffic on roads and the installation of road signs, and point 4.2 of the Annex to GKM Decree 83/2004 (VI. 4.) on the requirements for the design, application and installation of road signs.
filing an application:
Section 6(1) of ITM Decree 26/2021 (VI. 28.) on road administration provides for the content of the application for the consent of the public road operator for the use of the road area. According to this, the following details must be provided:
- location of use (municipality, parcel number, expressway number and km section; we recommend using the http://mkif.hu/terkep/, https://kira.kozut.hu and https://utszamkereso.kozut.hu websites for identification)
- the designer’s chamber number(s), licence(s) or designer’s declaration
- the name and address of the person requesting the consent, in whose interest the request is made (in the case of a natural person: name, address, telephone number, e-mail address; in the case of a legal person: name, registered office, company registration number, telephone number, e-mail address)
- the name and contact details of the person responsible for ensuring compliance with the conditions of the public road operator’s consent
Please submit the application for public road operator’s consent by post to MKIF Hungarian Concession Infrastructure Development Plc. (2040 Budaörs, Akron utca 2., Hungary) or digitally in pdf format to [email protected].
annex:
documentation prepared by a specialist designer (traffic engineering plan, layout sketch)
administrative time limits
According to Section 6(2) of ITM Decree 26/2021 (VI. 28.), the public road operator shall decide on the application within 21 days of receipt, which may be extended by the public road operator once by a maximum of 10 days.
The public road operator shall refuse consent if the planned use would result in a significant deterioration of the condition of the road, would cause serious damage to or would endanger the safety and continuity of road traffic, and this cannot be avoided by setting the conditions for use, and if the use would interfere with the performance of the public road operator’s maintenance and operational tasks or the implementation of its network development and modernisation plans and programmes.
Validity of the public road operator’s consent: until withdrawal