Please provide 1 working copy of the implementation plans to our Company at the latest before the provisional placing in service. The working copy must include a manual correction in red of any deviation from the original plans.
We request 3 hard copies of the final implementation plans for all disciplines for our Company:
- on 1 copy, the changes made during the construction should be marked in red in relation to the original construction plans (crossing out the planned data, indicating the values implemented), 2 copies of the implementation plans for the bridge construction
- 2 copies in black and white should only show the actual situation.
In addition to the paper documentation, we also request 1 copy in digital (editable (dwg, doc, xls) and non-editable (pdf) format.
Please submit the designs (drawings) in dwg format.
In addition, please ensure that digital designs in dwg format above meet the following requirements:
- surfaces can be calculated,
- documentation based on a geodetic survey
- 3D file in height base system according to EOV correct construction plans
- based on a current land registry base map
- hidden installations should be indicated with a pre-hiding measurement